Posted on November 11, 2026 by Shawn

Meeting Overview

The Albany County Board of County Commissioners met Monday, Nov. 9, 2026, rejecting a nearly $2.9 million design-build proposal for new fairgrounds grandstands and directing the county engineer to pursue a different procurement path. The board also approved a variance for an accessory building built without proper permits, a decision that drew pointed concern from Commissioner Pete Gosar about the precedent it sets. Across the meeting, commissioners authorized roughly $484,000 in new contracts, including a motor grader, a compensation study, and a demolition contract for the Thunderbird Motel.

Fairgrounds Grandstands Bid Rejected

The board declined a proposal from Capital Builders of Belle Fourche, South Dakota, to design and build new grandstands at the Albany County Fairgrounds for a guaranteed maximum price of $2,893,450. County Engineer Jake Schneider told the board the bid was deficient, lacking a required 5% bid bond and several other items.

Schneider said Capital Builders was the only bidder among six to eight companies that attended a pre-bid meeting. He recommended the county act as its own general contractor through a cooperative purchase agreement, buying the bleachers and separate components directly rather than relying on a single contractor. “I have more confidence in me than somebody who can’t even respond to an RFP,” Schneider said.

The decision matters to residents who use the fairgrounds, because Schneider warned that if the project slips a year, additional repairs would be needed to keep the existing grandstands safe. He said he told Prairie Equipment, the demolition contractor, not to begin work until all issues are resolved so the structure can be rebuilt and usable. The board voted to reject the Capital Builders bid as nonresponsive and pursue the cooperative purchase approach.

Thunderbird Motel Demolition Contract

The board approved a $148,782 construction contract with Prairie Equipment for asbestos abatement and demolition of the Thunderbird Motel, part of the Thunderbird Soup Kitchen redevelopment. Schneider said the project is funded through a grant and that Prairie Equipment was the lowest qualified bidder.

Commissioner Gosar asked where asbestos found during demolition would be taken. Schneider said it would likely go to the landfill, with specific handling instructions and a permit required through the state Department of Environmental Quality. The contract passed.

Cornerstone Trust Variance and Zoning Concerns

The board approved a variance for the Cornerstone Irrevocable Trust allowing an accessory building to remain within the required 10-foot setback at 392 Grant Street. Planning Director David Gertsch explained the building additions were constructed without zoning certificate approval and are currently in violation of the county zoning resolution.

Gertsch said the property is very small at 0.24 acres, and that similar small properties were not included in a neighborhood conservation district that allows zero setbacks. He concluded the encroachment is not detrimental to nearby property owners and that the small-lot hardship was not self-inflicted.

Commissioner Gosar pushed back, saying approving the variance undermines the zoning process because people could build first and seek a variance later. He asked whether there are financial penalties for building without a permit, and Gertsch said there is a $200 late fee for applications that come in late. Gosar said he wanted that penalty raised to something meaningful. “If you build and you didn’t have a billing permit, it’s thousands of dollars,” Gosar said. The variance passed.

Wall Canyon Ranch Rezoning

The board approved a zoning district amendment changing about 2.5 acres of the Wall Canyon Ranch from agricultural to industrial for a fiber regeneration station proposed by L3 Communications. Planning and GIS Specialist Jorey Unverzagt said the property sits within the North Laramie Sage Grouse core area, meaning future development must comply with the governor’s Executive Order 2019-3.

Unverzagt told the board the county has no mechanism to enforce the sage grouse order, which goes through Wyoming Game and Fish, and that the applicant would need to coordinate with that agency. The amendment passed.

Other Business

The board approved a $39,500 contract with Evergreen Solutions LLC to conduct a comprehensive classification and compensation study covering about 73 employee classifications. Human Resources Director Aneesa McDonald said six bids were received and three firms interviewed.

Commissioners awarded a bid of $295,546.41 to Wyoming Machinery for a Caterpillar 140 AWD motor grader, with delivery expected in early February and a corrected nine-year, 8,500-hour warranty. Road and Bridge Superintendent Jeremy Sellars said the grader replaces one with an expiring warranty.

The board also approved a liquor license transfer for the Snowy Range Ski Area from SkiWyo, LLC to SR Enterprises Holdings, LLC, conditioned on receiving a Forest Service lease agreement. Clerk Kayla White said the license would not be issued until that lease arrives.

Fairgrounds Director Taylor Heggie reported on the first year of an animal donation program, in which 11 animals were donated to community organizations including the school district, Cathedral Home, and the hunger initiative. Commissioner Gosar called the program “fantastic” and “great”.

Vote Summary

The board approved the Thunderbird Motel demolition contract, the compensation study award, the motor grader purchase, the Cornerstone Trust variance, the Wall Canyon Ranch rezoning, the liquor license transfer, and the wellness contract with Wyoming Health Fairs. The Capital Builders grandstands proposal did not pass.

Leave a Reply Cancel reply

You must be logged in to post a comment.

loader-image
Local Weather
Laramie, WY
10:56 pm, November 18, 2026
31°F
clear sky
31 %
1019 mb
7 mph
Wind Gust: 0 mph
Clouds: 0%
Visibility: 10 km
Sunrise: 6:54 am
Sunset: 4:41 pm

©2026 County 5 | Design: Newspaperly WordPress Theme