ROAD CLOSURE : 15th Street In 3 Phases Starting 3 July 6th
Beginning Wednesday July 6, 2023, thru Friday August 11, 2023, 15th Street will close, in phases, to allow Simon Contractors to complete water and sewer connections for the University of Wyoming Dorm project.
Phase 1 –South of Willett to Sorority Row – July 6 to July 19
Phase 2 – The intersection of Willett & 15th Street – July 20 to July 28
Phase 3 – North of Willett to Bradley – July 31 to August 10
A view of the phasing is available on the City of Laramie Street Closure Map.
Question/concerns to City of Laramie Engineering 307-721-5250, engineering@cityoflaramie.org